A specification must not require or refer to a particular trademark or trade name (ambiguous), patent, copyright, design or type, specific origin, producer, or supplier, unless there is no other sufficiently precise or intelligible way of describing the requirement. In an exceptional circumstance when this type of specification is used, words such as ‘or equivalent’ must be included in the specification.

Definition 2 as made · 22 October 2025 onwards

Definition history

  1. 22 October 2025 onwards

    Definition 2 as made

    Start commencement not settled: dated by registration or assent. Registered 22 October 2025.

    A specification must not require or refer to a particular trademark or trade name (ambiguous), patent, copyright, design or type, specific origin, producer, or supplier, unless there is no other sufficiently precise or intelligible way of describing the requirement. In an exceptional circumstance when this type of specification is used, words such as ‘or equivalent’ must be included in the specification.